Crop storage facility

12 December 2012

Materials processing and handling engineering company, GAME Engineering has been working with WoldGrain Storage since January 2010 on an integrated combined crop storage facility based at Hemswell, Lincolnshire. In

Materials processing and handling engineering company, GAME Engineering has been working with WoldGrain Storage since January 2010 on an integrated combined crop storage facility based at Hemswell, Lincolnshire.

In Jan 2010 GAME was awarded the Phase 1 contract to design, supply and install all the handling and processing systems. The project involved increasing the existing storage capacity to accommodate an additional 18,000t of combinable crops, including wheat, oilseed rape and malting barley. The upgrade involved increasing the intake capacity to 500t per hour, installing new handling and processing equipment rated at 100t per hour, and adding a new grain drier and blending system to maximise productivity.
 